YOUR JOURNEY TO OWNING A NEW AVELING HOME
-
1
YOUR NEW HOME FILE IS SUBMITTED TO ADMIN AND AN INDIVIDUAL PROJECT NUMBER ISSUED
-
2
SURVEY & ENGINEERS REPORT ORDERED
-
3
SURVEY & ENGINEERS REPORT RECEIVED
-
4
DETAILED WORKING DRAWINGS COMPLETED
-
5
ENGINEERS ASSESSMENT OF WORKING DRAWINGS COMPLETED
-
6
6 STAR ASSESSMENT OF WORKING DRAWINGS COMPLETED
-
7
SITEWORKS QUOTING COMPLETED
-
8
CONTRACT DOCUMENTS FINALISED
-
9
CONTRACT DOCUMENTS ISSUED TO CLIENT
-
10
CONTRACT DOCUMENTS (SIGNED) RECEIVED FROM CLIENT
-
11
CLIENT SUBMITS SIGNED CONTRACTS TO FINANCE LENDER
-
12
BUILDER SUBMITS WORKING DRAWINGS TO WATER CORPORATION
-
13
PLANNING APPROVAL APPLIED FOR IF REQUIRED
-
14
PLANNING APPROVAL RECEIVED
-
15
PRE-START SELECTIONS MEETING BOOKED Meeting
A-Colours and products Meeting B-Electrical and smart wiring
-
16
PRE-START MEETING FINALISED MEETING
Meeting A-Colours and products Meeting B-Electrical and smart wiring
-
17
AMENDED WORKING DRAWINGS FROM PRESTART MEETING SIGNED BY CLIENT
-
18
DEVELOPER APPROVAL APPLIED FOR IF IN A NEW HOUSING ESTATE
-
19
DEVELOPER APPROVAL RECEIVED IF IN A NEW HOUSING ESTATE
-
20
LAND SETTLEMENT CONFIRMED
-
21
BCA (BUILDING CODES OF AUSTRALIA) ASSESSMENT OF WORKING DRAWINGS COMPLETED
-
22
BUILDING LICENCE APPLIED FOR WITH LOCAL SHIRE
-
23
BUILDING LICENCE RECEIVED FROM LOCAL SHIRE
-
24
UNCONDITIONAL FINANCE APPROVAL RECEIVED FROM LENDER
-
25
CLIENTS PROJECT HANDED OVER TO CONSTRUCTION DEPARTMENT
-
26
(SINGLE STOREY)
EARTHWORKS COMPLETED
-
27
(SINGLE STOREY)
SLAB COMPLETED
-
28
(SINGLE STOREY)
BRICKWORK COMPLETED
-
29
(SINGLE STOREY)
PLATE HEIGHT COMPLETED
-
30
(SINGLE STOREY)
ROOF COVER COMPLETED
-
31
(SINGLE STOREY)
LOCK-UP COMPLETED (CABINETS/TILER/PAINTING COMPLETE)
-
32
(SINGLE STOREY)
FINALS COMPLETE (PLUMBING/ELECTRICAL COMPLETE)
-
33
(SINGLE STOREY)
PRACTICAL COMPLETION MEETING COMPLETED
-
34
KEY HANDOVER