• Yellow stages indicate regular communication from your Contracts Consultant
  • Blue stages indicate regular contact from your Pre Start Consultant
  • Green stages indicate regular contact from your Construction consultant

YOUR JOURNEY TO OWNING A NEW AVELING HOME

  • 1 YOUR NEW HOME FILE IS SUBMITTED TO ADMIN AND AN INDIVIDUAL PROJECT NUMBER ISSUED
  • 2 SURVEY & ENGINEERS REPORT ORDERED
  • 3 SURVEY & ENGINEERS REPORT RECEIVED
  • 4 DETAILED WORKING DRAWINGS COMPLETED
  • 5 ENGINEERS ASSESSMENT OF WORKING DRAWINGS COMPLETED
  • 6 6 STAR ASSESSMENT OF WORKING DRAWINGS COMPLETED
  • 7 SITEWORKS QUOTING COMPLETED
  • 8 CONTRACT DOCUMENTS FINALISED
  • 9 CONTRACT DOCUMENTS ISSUED TO CLIENT
  • 10 CONTRACT DOCUMENTS (SIGNED) RECEIVED FROM CLIENT
  • 11 CLIENT SUBMITS SIGNED CONTRACTS TO FINANCE LENDER
  • 12 BUILDER SUBMITS WORKING DRAWINGS TO WATER CORPORATION
  • 13 PLANNING APPROVAL APPLIED FOR IF REQUIRED
  • 14 PLANNING APPROVAL RECEIVED
  • 15 PRE-START SELECTIONS MEETING BOOKED Meeting
    A-Colours and products Meeting B-Electrical and smart wiring
  • 16 PRE-START MEETING FINALISED MEETING
    Meeting A-Colours and products Meeting B-Electrical and smart wiring
  • 17 AMENDED WORKING DRAWINGS FROM PRESTART MEETING SIGNED BY CLIENT
  • 18 DEVELOPER APPROVAL APPLIED FOR IF IN A NEW HOUSING ESTATE
  • 19 DEVELOPER APPROVAL RECEIVED IF IN A NEW HOUSING ESTATE
  • 20 LAND SETTLEMENT CONFIRMED
  • 21 BCA (BUILDING CODES OF AUSTRALIA) ASSESSMENT OF WORKING DRAWINGS COMPLETED
  • 22 BUILDING LICENCE APPLIED FOR WITH LOCAL SHIRE
  • 23 BUILDING LICENCE RECEIVED FROM LOCAL SHIRE
  • 24 UNCONDITIONAL FINANCE APPROVAL RECEIVED FROM LENDER
  • 25 CLIENTS PROJECT HANDED OVER TO CONSTRUCTION DEPARTMENT
  • 26 (SINGLE STOREY)
    EARTHWORKS COMPLETED
  • 27 (SINGLE STOREY)
    SLAB COMPLETED
  • 28 (SINGLE STOREY)
    BRICKWORK COMPLETED
  • 29 (SINGLE STOREY)
    PLATE HEIGHT COMPLETED
  • 30 (SINGLE STOREY)
    ROOF COVER COMPLETED
  • 31 (SINGLE STOREY)
    LOCK-UP COMPLETED (CABINETS/TILER/PAINTING COMPLETE)
  • 32 (SINGLE STOREY)
    FINALS COMPLETE (PLUMBING/ELECTRICAL COMPLETE)
  • 33 (SINGLE STOREY)
    PRACTICAL COMPLETION MEETING COMPLETED
  • 34 KEY HANDOVER